Point Hebdomadaire

UTC

Presents: Senol, Jehanne, , Wu, Mathias, , Amira, Manon, Sylvestre, Tristan

 

WP0: Management

  • Comments made by Senol & Sylvestre on the Project Management Plan: short meeting foreseen 
  • ESO visit @ LIRA/Meudon the 19/20 March
  • Link between SHARKS and PLANETS project
  • PBS to send to Luis in the current version

 

WP1 Metrology: Metrology

  • Bench description document under work, stil missing some data.
  • Meeting the 2sd of March

 

WP2 Beam Combiner: 

  • RAS
  • Polarization control is coming this week.
  • Amira next week at TeemsPhotonics to test a new component. Action: Write a test report please.

 

WP3 Spectrograph:

  • New optical design with telecentric design, have a look with ESO engineer on the design.
  • Contacts with sub-contractors, needs to have a first volume, depends on the facilities needed. Action Tristan: send first volume estimation to Luis.
  • FLI requirements document update, need information from Leonardo
  • Action Tristan: send to Derek some tests wanted to be performed on the detector @ESO

 

WP4 Feeding optics: 

  • RAS

 

WP5 ICS: 

  • RAS

 

WP6 System Test: 

  • Work on the ICD (Sylvestre & Tristan)

 

WP7 Pipeline: 

 

Other Business:

  •  
Il y a un compte-rendu associé à cet événement. Les afficher.
L'ordre du jour de cette réunion est vide