WP0: Management

  • Go thru the minutes of the progress meeting for the various comments

 

WP1 Metrology

  • Discussions with Pierre-Bourgé @ Paranal, good to have FSM as an option, piezo control system baseline
  • Check if possible to have 8m of harness between the electronic and piezo. If not --> Use FSM
  • Discussion around the optical fiber routing
  • Availability by end of July @ Paranal to help installing the hardware
  • Need authorisation from ESO --> How ask ? Need short document to explain the fiber routing.

 

WP2 Beam Combiner: 

  • No news
  • Laser source at the supplier to fix the problem
  •  

WP3 Spectrograph:

  • Last version of Zemax conf, optimisation of the collimator with two achromatic COST doublets
  • Very first mechanical implementation 
  • Action to have one unique document for all the spectrometer requirements.

 

WP4 Feeding optics: 

  • Nothing to say
  • Piezo stage will be delivered to Pierre @ Paranal to check the mechanical IF

 

WP5 ICS: 

  • Nothing to say

 

WP6 System Test: 

  • On the TLR document remarks from Luis:
    • Optical bandwidth
    • Need link to the metrology system
  • Where to put the components at the VLTI lab and on the PIONER bench ? Important to define the components.

 

WP7 Pipeline: 

  • Nothing to say

 

Other Business:

  • No