Point hebdomadaire

UTC

Presents: Luis,  Tristan, Zexuan, Senol, Luis, Sylvestre, Manon, Mathias, Amira, Jehanne

 

WP0: Management

  • Update of the PMP: FTE, PT, WBS.
  • New directory for the WP11 System Engineering -->  Here documents like TLR

     

  • Last check for the PMP document for next step to sign
  • Make all the issues in the JIRA web site: use product inside the PMP
  • Make a short Readme on the JIRA to help the use of it
  • Action Sylvestre: continue the instrument overview document

 

WP1 Metrology

  • Action Tristan : Put the tasks in Metrology_follow-up.xlxs under JIRA tickets
  • Elias to send @LIRA for 3D printing 
  • Wait to get big order to Thorlabs
  • Hugo is a new student working on the polarisation control
  • Linux WS with VLTI software to procure
  • Warning: Laser interlock
  • 500m optical fibers under procurement 
  • New about the issue on the laser

 

WP2 Beam Combiner: 

  • To begin CCTP for the sun-contractor
  • Work on the test of a new component

 

WP3 Spectrograph:

  • Optimisation of the Gravity collimator
  • Design update see onedrive document
  • Need to think about the AIT process

 

WP4 Feeding optics: 

  • Nothing to say more
  • Pre-Design by Pierre-Bourger, piezo-stage mechanical part received. The goal is to align and check.
  • No news about the control electonics

 

WP5 ICS: 

  • Nothing to say more

 

WP6 System Test: 

  • Global strategy to discuss about --> Thursday 23rd 
  •  

 

WP7 Pipeline: 

 

WP11: System Engineer 

  • Action Tristan : make a first draft of the document 

 

Other Business: Nothing.

  • Selection of PstDoc at ESO

 