Point Hebdomadaire

UTC

Presents: Luis,  Tristan, Senol, Sylvestre, Manon, Mathias, Jehanne, Elsa, Elias, Samuel, Annes, Antoine, Zexuan

WP0: Management

  • Comments from Senol about the PMP
  • Possible to share it by the end of the week
  • Presentation of the global schedule and associated reviews
  • Top level scientific specifications document to be release 
  • Technical requirements to wok on
  • ICD to work on
  •  

 

WP1 Metrology

  • First release of the document to be share soon
  • Test setup to be clarified, the test plan to come next (need information from Paranal to know how it may/will append)
  • Coordination between Luis and Amira
  • No more information --> Waiting for the springs
  • No news from Paranal for the routing of the optical fiber thru the telescope

 

WP2 Beam Combiner: 

  • Chip from ST the chip to be implemented with fiber by teemsphotonics --> JIRA ticket to follow the component :-) : Action Jehanne
  • Polarisation studies on the test-bench: polarisation at the output of the fiber is not linear (probably due to the collimator and not to the fiber itself). 

 

WP3 Spectrograph:

  • Meeting with Christian about the Gravity design.
  • Currently two custom designs --> See manufacturers to see what could be possible to build. Designs on the onedrive.
  • Meeting with FLI to talk about the mechanical IF and the deliveries of the different models
  • See if possible to have a smaller detector to integrate sonner or buy camera and make specific MGSE to mimic the final IF
  •  

 

WP4 Feeding optics: 

  • Have STEP file of the current design to test the concept here of the injection module with the piezo stages

 

WP5 ICS: 

  • Roberto to provide the WS

 

WP6 System Test: 

  • Discussion about what to build to mimic PIONER @ LIRA for system test
  • Options:
    • Built injection part only
    • Need to demonstrate in lab the high contrast: Need piezo, TT, ... to reproduce part of the injection in PIONER

 

WP7 Pipeline: 

  • NA

WP11: System Engineer 

  •  

 

Other Business: Nothing.

  •  

 