Point hebdomadaire
→
UTC
Presents: Luis, Tristan, Amira, Antoine, Elsa, Sylvestre, Elias, Jens, Senol, Hugo
WP0: Management
- Check the budget for the reporting
- Instrument quarterly report to be done: work done, to be done, schedule
- Discussions around the availability of UT for day time
- Informal talk given by Sylvestre
WP1 Metrology:
- Reception of all the components from Thorlabs, fiber on the track to arrive mid-July
- Implementation of 10-90% and attenuator, diode not saturated, update of the budget.
- Reconstruction of membrame vibration seen by the optical fiber via the PSD
- Insulation on-going
- Meeting on the receiver (Elias, Amira and Tristan).
- Meeting @ ESO around the WS and the fiber routing
- Need to test the piezo-mike with 18m cable length
- Check the power-supply for the piezo-mike control electronic --> Dedicated metrology meetin gon Wednesday 25/06
- Detector procurement and laser for the polarization measurement
WP2 Beam Combiner:
- No time to work on the bench last week
WP3 Spectrometer:
- Optical design on-going, optimisation
- Available support from ESO on the optical design
- Interface with camera definition enter in the detailled design
- Thermo-Mechancial simulation will begin soon
- Ask Leonardo to have a smaller detector to get the camera sooner
- Design of support structure will begin soon
WP4 Feeding optics:
WP5 ICS:
- One electrical engineer will arrive on the project soon from UNIDIA 80%
- Mettings foreseen with Roberto (Metrology WS) and G. Zins (Instrument WS)
WP6 System Test:
- Nothing to say
WP7 Pipeline:
- Information OK to format the data in ESO compatible standard
WP11: System Engineer
Other Business: Nothing.
- RAS