Point hebdomadaire

→ UTC

Presents: Luis,  Tristan, Amira, Antoine, Elsa, Sylvestre,  Elias, Jens, Senol, Hugo

WP0: Management

  • Check the budget for the reporting
  •  Instrument quarterly report to be done: work done, to be done, schedule
  • Discussions around the availability of UT for day time
  • Informal talk given by Sylvestre

WP1 Metrology: 

  • Reception of all the components from Thorlabs, fiber on the track to arrive mid-July
  • Implementation of 10-90% and attenuator, diode not saturated, update of the budget.
  • Reconstruction of membrame vibration seen by the optical fiber via the PSD
  • Insulation on-going 
  • Meeting on the receiver (Elias, Amira and Tristan).
  • Meeting @ ESO around the WS and the fiber routing
  • Need to test the piezo-mike with 18m cable length
  • Check the power-supply for the piezo-mike control electronic --> Dedicated metrology meetin gon Wednesday 25/06
  • Detector procurement and laser for the polarization measurement

 

WP2 Beam Combiner: 

  • No time to work on the bench last week

 

WP3 Spectrometer:

  • Optical design on-going, optimisation
  • Available support from ESO on the optical design
  • Interface with camera definition enter in the detailled design
  • Thermo-Mechancial simulation will begin soon
  • Ask Leonardo to have a smaller detector to get the camera sooner
  • Design of support structure will begin soon

 

WP4 Feeding optics: 

  •  

 

WP5 ICS: 

  • One electrical engineer will arrive on the project soon from UNIDIA 80%
  • Mettings foreseen with Roberto (Metrology WS) and G. Zins (Instrument WS)
  •  

WP6 System Test: 

  • Nothing to say

 

WP7 Pipeline: 

  • Information OK to format the data in ESO compatible standard

 

WP11: System Engineer 

  •  

 

Other Business: Nothing.

  • RAS

 

Il y a un compte-rendu associé à cet événement. Les afficher.
L'ordre du jour de cette réunion est vide