Point Hebdomadaire

→ UTC

Metrology:

Fiber is currently scheduled to arrive on the 26th of September. Amira is trying to push this date forward with the manufacturer.
Ideally the fiber should be delivered in the first week of September to meet schedule.

Stuff of the bench: what do we want to procure, test, ship?

For the test in Paranal, is the plan is to leave the bench in Paranal? Luis suggests that it is probably better to store the bench somewhere rather than letting it collect dust.

Still need to be tested in Meudon:
1 - add the polarizer
2 - add the vibration control
3 - noise budget
4 - redpitaya programming and tests

The plan for the metrology bench. It needs 2 days packging, 5 days ship to Garching, and needs to be shipped 7th October to Chile. So we typically have until the end of September for the tests in Meudon.

Procurement should be started for the piezo structure (aluminum 3d print). This typically needs 4 weeks. Elias confirms that the design is ready to be manufactured. Tristan is in charge.

Need a controller in Garching for testing which is the last missing piece for Roberto to develop the control software (laser delivered 18th of September).


Spectrograph:

For the spectrograph: priority id to do a basic opto-mechanical design and see with Barabara to get support to improve the design later on.

No tolerance analysis for now. The idea is to do a simplified a tolerance analysis, with only the most important parts (e.g. collimator). This was already checked manually, and it seems fine. Elias is not too worried about this, but this needs to be checked.

 