Meeting FLI/Leonardo/LIRA
Meeting on the 12th November 2026
Tracy new project manager for the PLANETES project.
Update of Leonardo
- ROIC characteristation is complet
- Power higher than 60mA
- More complicated to Programm the ROIC in windowing: use case shown by LIRA
- Only 16 outputs available on the ROIC: OK from LIRA
- Leonardo these issues may be corrected or not (depended on ESA decision). The current contract will not introduce these changes. However, if CNRS wanted the corrections adopted a metal mask change would be required which would incur a 12-18 month delay. This would be subject to additional cost to CNRS if not undertaken by ESA. --> No demand from LIRA for any modification on the detector.
- MCT Progress shows possible candidates for Engineering and Science Detector (only 15 pixels with insulation defect).
- TRB in March to present all the results and select the chip to be glued on the packaging
- Test equipment built on ESA contact: Cryogenic chamber, Proximity Elec+Readout Elec (ARCON TBC), pumping and integrated sphere, to test the ROIC, measure the dark current (stay light contamination).
- Leonardo readout: rejection of the first two frames of each acquisition. If use of Global Reset: no issue. Seems to be an issue from the proximity electronic and not located inside the ROIC
- LIRA would very like to have a much as possible information on the detector readout
- Contractual milestones: ROIC characterisations done, invoice sent to
- Need 10 weeks for the detector delivery after the reception of the packaging
- Action Tristan to check why the first invoice was rejected and if the contract may be
delayed by 2-3 monthsextended by 6 months for the final milestone. The request for extension is due to receipt of FLI packaging (advised April/May) at Leonardo and array assembly into the package (10 weeks upon receipt of packaging). Any additional delays to FLI packaging delivery to Leonardo will incur schedule delay to final milestone.
Update FLI on the packaging.
- Design expected in Feb-2027
- About 2 months for the procurement
- FLI needs some time to test the packaging.
- FLI will send the design to Leonardo
- First step to send a STEP file to check the feasibility @ Leonardo
- Expected date of delivery in April/May
Meeting on the 22sd of September 2026
Agenda:
- Status of the detector procurement
- Planning update
Minutes:
MCT new design for shortwave, one batch as pilot, new couple of weeks MCT grown on ROIC.
ROIC with some issues
- complete the characterisation.
- 16 outputs --> OK
- Pixel bias higher, more current in the pixel circuit, 140mW with 16 outputs and @250kHz, frame rate 1Hz. More or less constant with the pixel clock.
- Design can go up to 15Hz
- Mask works well to reduce the glow (here pixel induced glow --> Different than output glow effect).
- Seems possible to work in photon counting mode
- Characterisations document written, goes in the signature process, send to LIRA/FLI in few weeks.
Schedule:
- ROIC in December ready to receive the MCT.
- March 2027 TRB
- Need meeting in three weeks time to check everything keeps on tracks
FLI:
- Begin October to work on the design
- Validation of the packaging by supplier in March
- Design done by the end of the year
- Request 2 trial parts by Leonardo
- Issue on large capacitance to put at the detector output --> Find the right reference in cryogenic environment.
- Related to clock speed
- Noise on PRV acts directly on the noise at the output
- Management may be done by external Reset signal
- Sudden loss of Power-Supply --> No risk for the detector
New questions from FLI
-
Any update about:Sensitivity of the voltages ? --> See characterisations report of the ROIC
-
Slew rates at 3 MHz ? --> Only measured @ 270kHzPower dissipation at 270 kHz ? At 3 MHz ? --> See the minutesAre the drive capabilities in the two modes confirmed at 20 pF ? --> Source follower and output buffer modesWhat happens in case of sudden loss without respect of the Power-OFF sequence ? --> On going study, feeling that it's not an issue
-
Update about ROIC documentation ?
-
Update about the sensor datasheet ?
Questions and answers
- What is the size of the ROIC?
- What is the sensitivity of the output voltage to noise on PRV or common?
- Can you provide a drawing of the pin out of the ROIC?
- Can you confirm the dynamic range of the device:-
- Likely operating temperature of the device will be 70-80K
- Operating mode is unknown at present.
- What are the slew rates at approximately 3MHz clock rate (i.e. around 10 Hz)
- Drive capability in both buffered and unbuffered modes.
- Please provide a comparison table between buffered and unbuffered modes
- What are the implications of a sudden loss of supply to any of the supply voltages to the device?
Our interim answers are as follows:-
- 33840 x 37900 microns – to the edge of the saw lane, the likely size would probably range from this to this + 50mircons
- We have manufactured initial array samples, but haven’t yet measured this. For previous devices using a similar architecture, we have suggested <0.25mV for both.
- See the attached spreadsheet
- Dynamic range has been measured as 980mV @ 80K
- Not yet measured for this device, previous devices of a similar architecture have slew rates of around 4.3V/µs (rising) & 1.5 V/µs (falling)
- Not yet measured, simulated at around 20pF
- Table will be available shortly
- We don’t believe this will be a problem, but are planning a test to confirm this
Questions and answers
- Consolidation of the manufacturing planning and batches (engineering and science) and strategy of choice of the two detectors.
- Probably easiest to discuss this at the meeting suggested by Tristan
- Typical cosmetic evolution with respect to the temperature
- Generally, signal (QE and gain) defects remain consistently high and independent of temperature up to 120K and even 130K on some arrays. In extreme conditions where the array is limited by dark current there will be an increase in noise defects with temperature, but this depends very strongly on the operating conditions
- Typical curves for Gain-Bias, Gain-Dark, Gain-Cosmetic.
- In APD designs for astronomy the avalanche gain exponent is 0.30-0.34. The dark current receives very little avalanche gain. Typical noise figures are in the region of 1.0-1.1 and therefore contribute very little to the signal/noise. I assume your question relates to the maximum usable gain which is the highest gain that produces the maximum number of noise defects that can be tolerated – this clearly depends on the conditions and application.
- Typical quantum yield curve for a cut-off wavelength of 2.5µm
- J-band and H-band 90%, K-band 83%
- Typical curve of readout noise versus pixel frequency
- We typically measure this at 1 or 2 spot frequencies during the characterisation; I have noted your planned frame rate and included this in the characterisation plan
- Typical use of reference lines
- The reference lines can be readout in sequentially with the main array, i.e as a 2056 x 2048 array. The four reference rows top and bottom consist of a silicon only pixel design, allowing the noise of the silicon pixel to be deducted from the MCT array data
- DCI for mechanical and electrical interfaces (ROIC Pin-out description)
- I’ve attached the pinout as an excel spreadsheet, the X & Y co-ordinates of each pad are contained within the spreadsheet, referenced to the optical centre of the array.
- Reference of the ADC to match to the readout noise of the detector
- Power dissipation of the detector (maximale, with 16 outpits)
- This strongly linked to the expected frame rate, for example, we would expect around 40mW @ 1Hz( depending on the mode of operation)
- Analog outputs slew rate value (consolidated)
- 1.1-2.8V/µs from the previous iteration of ROIC (depending on output mode etc), will be confirmed on the latest design once the characterisation is complete
- Information on the internal thermal sensor of the detector
- Internal temperature sensors are no longer offered on the ME1230, we are able to provide 1 or 2 temperature sensing diodes, co-located on the focal plane, next to the ROIC
- New version of the ROIC data-sheet available (confirmation of the various TBC)
- The ME1230 ROIC is about to start characterisation, initially as a bare ROIC and later with trial CMT mounted to it, the datasheet will be updated at that point, however we will attempt to deal with any specific question sin the meantime if possible.
I add one more :
- Are we still limited to 20 pF parasitic capacitance on the video channels in output buffer mode?
- The parasitic capacitance could be allowed to increase a little, however this will place increased load on the output buffers, increasing the overall power consumption and potentially increasing the glow that the pixel array is subjected to. It will also limit the slew rate and hence limit the maximum frame rate
Meeting July 2026
IF status:
1)- Only in draft version, new version expected in 3-5 weeks from now
2)- Packaging 2kx2k, new design not started yet. schedule to be done. Dimension of the ROIC to be given. FLI has no date for packaging delivering, design begin in September, schedule updated after feed-back from the manufacturer. Detector delivered by begin of 2027, TRB in January/Feb 2027. FLI send the packaging with transportation box to Leonardo and travel back to FLI, Leonardo need some spare packaging/box to checked the mounting procedure. FLI ask some mechanical model of ROIC to check the cooling on the packaging.
3)- Technical question on the power-down sequence: what can happened if the procedure is not respected in case of failure ? --> Leonardo to checked.
Stability of the PRV (TBC?) bias ? --> Leonardo: gain is proportional to PRV-Substrat, so PRV bias is very sensitive.
Pinout of the 2kx2k ROIC needed by FLI --> To be send by Leonardo
ROIC capability of the outputs ? --> Part of ROIC characterisations, probably not large changes from current numbers, update of the analog characteristics of the outputs in the next few weeks.
4)- Next ROIC will come with non-buffered mode (better for low flux).
5)- Need to have a meeting after some progress in the packaging design @ FLI
Minutes proposal.
1)- Documentation.
The ROIC documentation is already in draft, new version expected in 3-5 weeks from now
2)- Design
The new design of the packaging 2kx2k not started yet. The dimension of the ROIC to be updated in the documentation.
Detector delivered by begin of 2027, TRB in January/Feb 2027:
- FLI send the packaging with transportation box to Leonardo
- Leonardo integrate the detector inside the packaging
- Leonardo send back the detector inside its transportation box to FLI
Leonardo need some spare packaging/box to checked the mounting procedure. FLI ask some mechanical model of ROIC to check the cooling on the packaging.
Leonardo: Detector deliveries will only be able to begin once the packaging is available to Leonardo UK, to support this Leonardo would require design document for the packaging in Oct 26 and the packaging delivered at the last in Jan 27. Any delay to these dates will delay the delivery of the completed array.
Technical question on the power-down sequence: what can happened if the procedure is not respected in case of failure ? --> Leonardo to checked.
- Stability of the PRV (TBC?) bias ? --> Leonardo: gain is proportional to PRV-Substrat, so PRV bias is very sensitive.
- Pinout of the 2kx2k ROIC needed by FLI --> To be send by Leonardo
- ROIC capability of the outputs ? --> Part of ROIC characterisations, probably not large changes from current numbers, update of the analog characteristics of the outputs in the next few weeks.
4)- Next ROIC will come with non-buffered mode (better for low flux).
5)- Need to have a meeting after some progress in the packaging design @ FLI
6)- Actions list.
Action Leonardo:
- Update the ROIC documentation (beginning of September)
- Answer to the technical questions (mid-September)
Action FLI: Give the schedule of the camera development including the packaging design and procurement (beginning of September)
Meeting on the 12th of November 2026
Presents: Tracy, Greg, Dan (Leonardo),Lucie (FLI), Sylvestre and Tristan
Tracy new project manager for the PLANETES project.
Update of Leonardo
- ROIC characteristation is complet
- Power higher than 60mA
- More complicated to Programm the ROIC in windowing: use case shown by LIRA
- Only 16 outputs available on the ROIC: OK from LIRA
- Leonardo these issues may be corrected or not (depended on ESA decision)
- MCT Progress shows possible candidates for Engineering and Science Detector (only 15 pixels with insulation defect).
- TRB in March to present all the results and select the chip to be glued on the packaging
- Test equipment built on ESA contact: Cryogenic chamber, Proximity Elec+Readout Elec (ARCON TBC), pumping and integrated sphere, to test the ROIC, measure the dark current (stay light contamination).
- Leonardo readout: rejection of the first two frames of each acquisition. If use of Global Reset: no issue. Seems to be an issue from the proximity electronic and not located inside the ROIC
- LIRA would very like to have a much as possible information on the detector readout
- Contractual milestones: ROIC characterisations done, invoice sent to
- Need 10 weeks for the detector delivery after the reception of the packaging
- Action Tristan to check why the first invoice was rejected and if the contract may be delayed by 2-3 months for the last milestone
Update FLI on the packaging.
- Design expected in Feb-2027
- About 2 months for the procurement
- FLI needs some time to test the packaging.
- FLI will send the design to Leonardo
- First step to send a STEP file to check the feasibility @ Leonardo
- Expected date of delivery in April/May