Point Hebdomadaire

→ UTC

Presents: Samuel, Amira, Senol, Sylvestre, Mathias, Tristan, Aneez, Zexuan, Luis.

 

WP0: Management

Need presentations for the progress meeting by the end of the week.

Sylvestre contacted few researchers at IRAP to find scientists involved in the project as Co-I, possible involvement of IRAP in the mechanical design of the polarisation control module.

Procurement of the cryostat may be done by LIRA.

WP1: Metrology

IF Mecca with spider parts received --> Send to Paranal with Pierre Bourgé to check the parts. Need to have a second exemplary including the modifications.

Receiver parts at the UNIDIA workshop for modification: waiting from UNIDIA feed-back. 

Optical fiber with jacket and connectors: waiting for quotation. 1km optical fiber arrive next week, then send to company to make the connectorisation, put jacket on the specified segments of optical fiber lengths. 

February tests: Two fibers in different jacket. Next step to put all the fibers for all the telescopes.

November to send the whole receiver system (mobile, receiver + Spider IF + Piezo-Mike + Cables) at Paranal by Luis.

Bench under integration with the new protection box, no really need to have polarisation control for the first test.

 

WP2 : Beam Combiner

Meeting with teamphotonics on the second of October.

First version of the call for tender document to discuss with team photonics

 

WP3: Spectrometer.

Cryostat feedthrough already done for MOONS project, seems to be good for Planetes.

Issue on the spectrum sampling. Optical design need to be checked.

Meeting with FLI for the camera development last week, specific meeting on the camera IF this week.

Meeting with Leonardo this week on the detector procurement.

In test: use test camera or 512x512 Leonardo.

Action Sylvestre: Give the exact reference of the test camera for the spectrometer AIT

Cryostat status: need discussion with Marcus. Need to write the call-for-tender document for the cryostat procurement.

 

WP4: Feeding optics

Discussions with VLTI.

How to replicate the injection bench ?

Action Sylvestre: Organise meeting with Pierre Bourgé and the Planetes team to talk about the Double Injection Module and the replication of the injection bench in Meudon for the instrument AIT.

 

WP5: ICS

 

WP6 : System test - Pipeline.

No news about the security officer @ Paris Observatory...

 

 

 

 

 

 