WP0: Management

PDM management.

Senol send templates for the progress meeting and  for the progress report --> Put on gitlab, dead-line for the next progress report is end of November. Sylvestre and Tristan to manage locally the filling of the document.

Main purpose: Schedule consolidation to have clear view of the progress in the WPs.

Action Tristan: Send the computer (used by Elias) to ESO

Romain will join soon the project. ESO new organisation at Paranal.

 

WP1: Metrology

TTR submitted to Paranal (one for test in March and one for WS installation).

Optical fiber available and send to SEDI company to install the connectors and put the jacket. 4-6 weeks to install the jacket on the fiber and then few weeks to install the connector (around 10 weeks).

Connectors under choice: E2000 to consider rather than FC/APC (TBC).

Demonstration of optical fiber machine to install connectors, to weld fibers, ...

Laser on the bench, installation on the network to remote control. Tests to be done (noise level estimation). Mechanical parts will be modified (tapped holes, new footprint for the springs) by this week. No news for the shielding of the bench.

Action Amira: Write the tests to be done on the laser with an associated schedule.

WP2 : Beam Combiner

Bi-refringence issue origin under study.

Argon source received, check the flux

Polarization control module under IRAP responsibility, to organise by end of November.

WP3: Spectrograph.

Report from Elias available on the onedrive --> Send directly to Yohann Komalsky (name TBC)

CCTP (call for tender) for cryostat procurement written. Waiting green-light from Markus before publishing the call for tender document. Procurement will be done by CNRS office.

Optical design: organise regular meeting with Yohann from ESO

Preliminary modelling of the support structure on-going to determine the shape and material of the blade --> Need to have regular meeting between LIRA and ESO on the opto-mechanical architecture.

WP4: Feeding optics

Optical Table new population done.

WP5: ICS

No news.

WP6 : System test - Pipeline.

 

 

 

 

 

 

 