Point Hebdomadaire
→
UTC
Presents: Senol, Sylvestre, Romain, Samuel, Mathias, Jehanne, Jexuan, Amira
WP0 Management
- Progress Report in Draft version
- Work on the global instrument schedule, beginning of the Pioner de-comissionning begin in 2028 (expected date).
- Progress meeting expected in mid-January
WP1 Metrology
- Begin to install the insulation box on Wednesday
- Work on software of alignment of the receiver.
- Oder the 7km of optical fiber
- Installation of the new springs in the next days (1 only has the right length)
- Need to built 3 mechanical receivers (1 spare), two piezo sets, 3 polarisers to buy
Action Amira: Make the order for optical components to build 3 receivers
- Discussions around the receiver - Telescope AIT.
- New computer to be send for the Metrology WS, Romain & Roberto to start the ICS
- Working meeting on the 19th November around the mechanical implementation
Action Amira: Optical fiber with APC/PC Thorlabs, then SEDI
WP2: Beam Combiner
- Order the PAX on-going, need other quotes from other company.
- Oder the optical fiber to test for bi-refringence
- Characterisation by the end of the month
- Bench results presentation
WP3: Spectrometer
- New design of the support structure
- ESO work on the support of the optical components
- New a regular meeting on the spectrometer (2 x weeks), need Johan on the optical design
- Need to define the IF between LIRA and ESO (Barbara)
And of the meeting...