Point hebdomadaire
→
UTC
Presents: Antoine, Senol, Luis, Jens, Jehanne, Roman, Zexuan, Cynthia
WP0 Management
- Progress report on-going, schedule to be consolidated, one for the global projet & one per each WP.
- Send invitation and agenda for the next progress meeting. People form ESO Tech-Dev department to addend to the meeting. TTR activities with ESO@Paranal people. Discussions on-going for the Metrology test next year.
WP1 Metrology
- New receiver part under test on the bench.
- Polirazier procurement on-going, collimator 2 in lab.
- Cover to protect the bench under construction
- Optical fiber for sending to Paranal received in Meudon --> TBC
- Expedition 12th of February, possible on the 8th of December.
- Path for the connexion on the spider may be longer. See the maximal cable length 18m
- Discussion around the Interlock. Laser IF to be send, standard IF.
- WS Metrology should arrived soon.
- June and Nov 2027 for the test on two UTs
Action Luis: Give an estimation of the piezo-mike cable length needs
WP2 Beam Combiner
- Polarimeter procured, wait to some components, fibers received
- Start STChip characterisations next week.
WP3 Spectrometer.
- Tolerancing on-going.
- Estimation of defocus
- Manufacturer proposed different material for the Lens.
- Information on Thorlabs Lens about vacuum-Temp, tests expected under environment conditions @ ESO.
- Feedthrough done @ SEDI company.
- FLI will deliver the detector packaging by 1.5 month, to delay the detector and camera procurement.
WP4 Injection Bench
- New design sent by Pierre, prototype will be tested, next year for the design and procurement of the final model.
- Discussions with IRAP on the documents sent for clarification.
- Need to get sub-systems from Pioner for the instrument integration in Meudon, need synchronisation between the activities. All duplicate will be very expensive.
- Beam selection: dichroics. Need clarification for the work done @ ESO and project. Requirements for dichroic as a good starting point.
WP5 ICS.
- New version of the Design Report: new stage on the double injection module and final Metrology board requirements.
- Work @ UNIDIA on stratégy of PI control and call-for-tender for the final Metrology control electronic
WP6 Pipe-line
- Some test last week.