Minutes of the progress meeting 29th September 2026

Presents: Senol, Sylvestre, Jens, Luis, Samuel, Amira, Jehanne, Elsa, Mathias, Tristan, Roberto

 

Senol.

  • General news of the project.
  • Metrology test posponed —> Feb 2027
  • Progress in design.
  • New people in ESO team: 2 x Post-Doc arriving in the next months
  • Metrology test preparation TTRs documents by end of October-2026
  • SDR/PDR posponed begining of 2027
  • Need to update the schedule of the WP with more granular view.

 

Action to each WP responsible: 

  • See slide 7 of Senol presentation to built the next progress report.
  • New progress to be written by end of November 
  • Built a realistic schedule 

 

Sylvestre.

  • Top-Level Requirements document and science cases
  • Metrology work-station can work without the instrument 
  • Instrument overview
    • Metrology WS algorithms and IF
    • Hardware from PIONIER not before 2028

 

Action Sylvestre: Organise a specific meeting for the Metrology WS setup.

Mathias & Amira for the Metrology ;-)

  • Presentation of the metrology concept
  • Injection module inside the instrument
  • Position control is more optical alignment --> To put inside the Metrology WS to have a stand-alone system.
  • Better to bring everything to Meudon to make a global test of the system, need the long optical fiber.
  • RedPytaya and Scope only used for the first test
  • For the first prototype test --> Do not use any polarisation control
  • Easy beam combiner easy to build for monochromatic beam
  • Power and noise budget. Info on Laser frequency noise.
  • Presentation of the metrology bench and noise injection to mimic and retrieve the vibration information
  • Procurement of the bench components on-going, expected to have all in the following weeks.
  • Need specific part to attach the receiver.
  • Receiver safety has been checked by Markus @ ESO-Garching, but need a double check from ESO-Paranal
  • Dead-line to send the optical fiber to Paranal, check is compatible with the optical fiber procurement

 

Action Luis: Need to clarify the interaction with Gravity during the metrology test.

Action Tristan: Write a technical note on the receiver parts for security and AIT check @ Paranal

 

Luis on Metrology test

  • CCB & TTR Status, schedule of the metrology prototype test/validation
  • Consolidation of the time-line @ Paranal
  • Some IF have to be checked.
  • Test on AT is considered but not at the moment ;-), let's focus on the UT

 

Action Luis: Prepare a check (or wish ? ;-) )list for mid-November

Action Mathias: For the test expected in summer 2027, do we need a specific electronic board or do we use multiple RedPytaya/Scope ? If specific board needed the work on it has to begin soon...

 

Tristan

 

Jehanne.

  • Test bench to simulate the VLTI --> Optimisation of the fringes contrast
  • Test of Gravity setup to control the polarisation --> Sensitive to optical fiber geometry configuration 
  • Test of "spring-like" setup --> More robust by bi-refringence observed (TBC) inside the optical fiber
  • Next steps to understand the "bi-refringence" on specific setup of the bench trying to induce this effect

 

Amira

  • Teamphotonics will realise all the beam combiner components we need ;-)
  • Characterisations of the chip --> Transmission
  • Beam combiners: one for the planets and one for the star
  • Phase shift under study --> Issue on people at the company put the PLANETES chip in stand-by
  • Metrology chips under realisation.

 

Conclusion

  • Focus on key milestones for the metrology
  • Progress report: Risks, schedule, expected actions/works (template from Gravity as exemple)
  • List of critical components and IF

 

Action Tristan/Sylvestre: Make an update of the cost of the instrument

 